Title
Multistage Long-Term Expansion Planning of Electrical Distribution Systems Considering Multiple Alternatives
Date Issued
01 May 2016
Access level
open access
Resource Type
journal article
Author(s)
Tabares A.
Franco J.F.
Lavorato M.
Universidad de Campinas
Publisher(s)
Institute of Electrical and Electronics Engineers Inc.
Abstract
This paper presents a new mixed-integer linear programming (MILP) model to solve the multistage long-term expansion planning problem of electrical distribution systems (EDSs) considering the following alternatives: increasing the capacity of existing substations, constructing new substations, allocating capacitor banks and/or voltage regulators, constructing and/or reinforcing circuits, and modifying, if necessary, the system's topology. The aim is to minimize the investment and operation costs of the EDS over an established planning horizon. The proposed model uses a linearization technique and an approximation for transforming the original problem into an MILP model. The MILP model guarantees convergence to optimality by using existing classical optimization tools. In order to verify the efficiency of the proposed methodology, a 24-node test system was employed.
Start page
1900
End page
1914
Volume
31
Issue
3
Language
English
OCDE Knowledge area
Ingeniería de sistemas y comunicaciones Ingeniería eléctrica, Ingeniería electrónica
Scopus EID
2-s2.0-84938808487
Source
IEEE Transactions on Power Systems
ISSN of the container
08858950
Sources of information: Directorio de Producción Científica Scopus